Paper Roads & Phantom Projects: Inside a Citizen’s RTI Battle for Panchayat Accountability in Mirzapur

Digital portals promise total transparency. Meanwhile, local notice boards list Paper Roads & Phantom Projects as completed work. What happens when a citizen asks for real receipts? This case study from Gram Panchayat Bihasada Khurd in Uttar Pradesh reveals the gap between digital promises and real-world honesty.

Key Takeaways

  • Digital portals in India promise transparency, yet local boards list uncompleted projects as finished, creating discrepancies in accountability.
  • Residents of Gram Panchayat Bihasada Khurd uncovered significant issues by verifying online claims against actual conditions, highlighting failures in the reporting system.
  • The case reflects broader rural administrative problems, prompting calls for mandatory verification of public disclosures and accountability for false reporting.
  • Stalling tactics and delays in responding to RTI requests undermine the spirit of transparency, often leaving citizens without vital information.
  • To ensure genuine grassroots transparency, officials must enforce rigorous standards to align public records with actual project completions.

Introduction: Paper Roads & Phantom Projects in Digital Transparency

Over the past ten years, India moved its rural government systems online. As a result, officials created sites like eGramSwaraj and set up village Public Information Boards (PIBs). These tools carried a simple promise. Specifically, villagers could track every rupee spent without visiting government offices. However, local realities often reveal issues like Paper Roads & Phantom Projects, where online reporting fails to match actual infrastructure development.

On paper, this system seems perfect. In practice, online data is only as accurate as the workers who type it in. Residents of Gram Panchayat Bihasada Khurd (Block Chhanbey, District Mirzapur, Uttar Pradesh) checked online claims against real work. Consequently, they found serious problems. For example, public boards showed unfinished projects as done. Furthermore, budget numbers did not match up. At the same time, officials routinely bypassed the Right to Information (RTI) Act, 2005 to avoid sharing basic financial records.

Core Issue 1: Paper Roads & Phantom Projects—The Public Information Board Mirage

Under Section 4 of the RTI Act, public offices must publish accurate data on their own. Because of this, citizens should not need to file formal requests. In rural areas, physical and digital Public Information Boards serve as the main tool for this openness.

However, legal hearings before the Uttar Pradesh State Information Commission (UPSIC) in Second Appeal No. S09/A/0494/2025 proved how quickly public displays can mislead people. When asked about work listed for FY 2022–23 in Bihasada Khurd, the Gram Panchayat Adhikari (Village Secretary) submitted a written reply on 10 May 2026. Remarkably, his reply included a direct official admission.

Paper Roads & Phantom Projects: Uploading the Wrong Village’s Board

  • The Wrong Village’s Board Was Uploaded: The Secretary admitted that staff made a technical mistake. Consequently, workers uploaded the Public Information Board of Gram Panchayat Bagedha Khurd onto the official page for Bihasada Khurd, creating false records of Paper Roads & Phantom Projects.

Paper Roads & Phantom Projects in Practice

  • Phantom “Completed” Projects: The official board for Bihasada Khurd listed several building projects under “Details of Work Done” (कराये गये कार्य का स्थलीय विवरण) with costs. These costs included Rs. 1,00,000 for drains and Rs. 70,000 for soak pits. Additionally, the board listed Rs. 1,90,000 and Rs. 1,20,000 for brick roads, plus Rs. 50,000 for a water pump and tank. In his written reply, however, the Secretary admitted that workers spent zero rupees on these tasks during FY 2022–23. Instead, he claimed the numbers only showed an initial proposal.

Unexplained Cost Variances and Missing Dates

  • Unexplained Cost Variances and Missing Dates: Even where authorities spent money, actual costs differed greatly from public signs. For instance, painting work on the Panchayat Bhawan appeared on the board at Rs. 1,90,000. However, official receipts showed a payment of only Rs. 32,750 on 10 March 2023. On the other hand, pump repairs listed at Rs. 35,000 jumped to Rs. 55,202 across 17 spots. This total included Rs. 38,682 for parts and Rs. 16,520 for labor. Still, officials failed to provide exact repair dates or GPS locations to confirm the work.

In the end, listing unbuilt projects as finished does more than confuse locals. Furthermore, it creates a fake paper record. This blocks social audits by villagers who rely on physical boards rather than complex databases.

Core Issue 2: Paper Roads & Phantom Projects through Unexplained Budget Anomalies

A closer look at financial reports on eGramSwaraj for Gram Panchayat Bihasada Khurd over four years (2022–23 to 2025–26) raised deeper concerns. Portal summaries showed total assigned funds of Rs. 1,33,65,400. Meanwhile, total reported spending reached Rs. 37,08,141 (Rs. 22,42,450 in FY 2022–23; Rs. 1,91,572 in FY 2023–24; Rs. 12,13,279 in FY 2024–25; and Rs. 62,040 in FY 2025–26).

In addition, big gaps appeared between Scheme-Wise Budgetary Allocations and Plan Outlays:

  • For instance, in FY 2024–25, the Panchayat’s “Own Funds” budget was set at Rs. 18,50,000, but the Plan Outlay jumped to Rs. 28,00,000.
  • Similarly, in FY 2023–24, the “Own Funds” budget was listed as Rs. 8,00,000, but the Plan Outlay dropped sharply to just Rs. 6,500.

Furthermore, online portals show summary tables, but citizens cannot inspect primary spending records. These records include Measurement Books (MBs), Work Completion Certificates, Bank Reconciliation Statements, certified payment vouchers, and audit reports. Therefore, an applicant filed an 8-point RTI request (DIRPR/R/2026/63290) on 20 July 2026 with the District Panchayat Raj Officer (DPRO), Mirzapur. Consequently, this request sought to verify the spending of Rs. 37.08 lakh and check actions taken regarding false notice board entries.

Core Issue 3: Paper Roads & Phantom Projects and Stalling Tactics

In fact, events after filing RTI request DIRPR/R/2026/63290 show classic administrative stalling tactics. Specifically, officials tire out citizens and weaken information laws without issuing direct refusals.

Paper Roads & Phantom Projects: Strategic Silence Past the 30-Day Deadline

  1. Strategic Silence Past the 30-Day Deadline: Under Section 7(1) of the RTI Act, 2005, a Public Information Officer (PIO) must reply within 30 days. However, DPRO Mirzapur completely missed the 19 August 2026 deadline. Consequently, this delay triggered an automatic refusal under Section 7(2). It also gave the applicant the right to receive records free of charge under Section 7(6).

#Paper Roads & Phantom Projects: The 81-Day Section 6(3) Transfer

  1. The 81-Day Section 6(3) Transfer: Indeed, the DPRO’s office responded only after the applicant filed a First Appeal (DIRPR/A/2026/63586) on 27 September 2026. Later, on 9 October 2026—a full 81 days after getting the request—the DPRO sent Letter No. 2893. This letter used Section 6(3) to pass the request to the Village Secretary. However, Section 6(3) requires transfers “in no case later than five days” after receipt. Ultimately, transferring the case three months late is invalid. It simply pushes responsibility down to lower staff.

Paper Roads & Phantom Projects: A Glaring Conflict of Interest

  1. A Glaring Conflict of Interest: Even worse than the delay was the way officials transferred the questions. Specifically, Point 7 asked for audit reports from the Audit Wing of the Panchayati Raj Department. Meanwhile, Point 8 asked for action details about the false notice boards. By sending Point 8 to the Village Secretary, the DPRO asked the accused officer to report on himself.

# Paper Roads & Phantom Projects: The “REQUEST DISPOSED OF” Mirage

  1. The “REQUEST DISPOSED OF” Mirage: Soon after, on 12 October 2026, the DPRO closed the case on the UP RTI Online portal as “REQUEST DISPOSED OF”. He uploaded a note stating: “महोदय आप की सेवा में प्रकरण प्रेषित है” (“Sir, the matter is forwarded to your good self”). Consequently, the citizen got no real answer, yet official metrics listed the case as resolved.

Core Issue 4: Toothless Appellate Orders and the Road to the Information Commission

When the First Appellate Authority (FAA)—the Deputy Director (Panchayat), Vindhyachal Division, Mirzapur—reviewed the First Appeal, procedural errors were obvious. In an order signed on 15 October 2026, the FAA ordered DPRO Mirzapur to supply the requested information within one week (by 22 October 2026). The order also warned of fines under Section 20 of the RTI Act.

However, the order suffered from two major flaws common in local RTI appeals regarding Paper Roads & Phantom Projects. First, the FAA issued it without holding a hearing (violating Rule 7 of UP RTI Rules, 2015). Second, it had no real enforcement. As a result, the 22 October 2026 deadline passed with zero compliance. Thus, the applicant escalated the case to the Uttar Pradesh State Information Commission. They filed Second Appeal Registration No. A-20261103225 on 25 November 2026.

Conclusion: Eliminating Paper Roads & Phantom Projects to Make Grassroots Transparency Real

The case of Gram Panchayat Bihasada Khurd is not an isolated mistake. Instead, it highlights a widespread problem in rural administration. Sites like eGramSwaraj and RTI Online were built to empower people. They were not meant to generate fake figures while basic records stay hidden.

If rural transparency is to work, three main changes are necessary:

  1. Mandatory Verification of Public Disclosures: Senior officers must hold local staff personally responsible. This applies whenever notice boards show unbuilt plans as finished projects or display data from other villages.
  2. Zero Tolerance for Late Transfers and Fake Closures: Information Commissions must deal strictly with late transfers and empty portal closures. Specifically, they should punish these actions as intentional delay under Section 20(1) and 20(2) of the RTI Act.
  3. Enforceable Physical Inspections: When officials hide behind summary tables, authorities must guarantee supervised physical checks. These checks must cover Measurement Books, cash books, and vouchers under Section 2(j)(i), alongside free certified copies under Section 7(6).

Until notice boards match ground reality and officers face real penalties, village development funds remain at risk from Paper Roads & Phantom Projects. This happens not because laws are missing, but because officers refuse to follow them.

Subject: RTI & Second Appeal Proceedings — Gram Panchayat Bihasada Khurd, Block Chhanbey, District Mirzapur (U.P.)

Applicant / Appellant: Ashok Kumar Maurya (+91-9619971441 | ashokkumarmaurya9619971441@gmail.com)

1. Application, Appeal & Official Reference IDs

Current Primary Case Chain (Audited Expenditure Records on Paper Roads & Phantom Projects, FY 2022–23 to 2025–26)

Paper Roads & Phantom Projects Case — Stage 1: Initial RTI Filing & Transfer

The primary case chain regarding audited spending records for FY 2022–23 to 2025–26 began with the Original RTI Application (u/s 6(1)) under registration number DIRPR/R/2026/63290. The applicant filed it before the SPIO / DPRO Mirzapur with 8 points on 20/07/2026. Furthermore, the associated RTI Online Transaction ID for this filing is DIRPRR20260000003929, dated 20/07/2026.

Paper Roads & Phantom Projects Case — Stage 2: First Appeal & Appellate Directives

Subsequently, the applicant submitted a First Appeal (u/s 19(1)) with registration number DIRPR/A/2026/63586 on 27/09/2026 to the FAA / Deputy Director (Panchayat), Mirzapur. In response, the DPRO sent a Late Transfer Letter (u/s 6(3)) under reference 2893/पं0-7/जनसूचना/2026-27 after 81 days on 09/10/2026. Consequently, officials marked the request disposed on the portal on 12/10/2026.

Paper Roads & Phantom Projects Case — Stage 3: Second Appeal & State Information Commission Proceedings

Following this, the First Appellate Authority (FAA) Order under reference DIVMZP-DDPOTS(RTI)/2/2025-DDP-DIVMZP (Ref: 1/1532566/2026) was issued on 15/10/2026. This order directed DPRO Mirzapur to supply information within 1 week (by 22/10/2026). However, due to non-compliance, the applicant filed a Second Appeal (u/s 19(3) before UPSIC) under registration number A-20261103225. This submission occurred online at 10:40:42 AM on 25/11/2026 with an online hearing option. Additionally, the applicant’s account ID on the UPSIC CATS portal is UPSIC Citizen Portal Account IDUPICR20240009954.

Regarding related and prior case references, an applicant filed a Related Audit RTI (u/s 6(1)) bearing registration number COMRD/R/2026/61040 on 26/06/2026 before DDO Mirzapur, which was closed on 17/07/2026. Subsequently, the DDO Mirzapur Transfer Letter under reference 548/आर०टी०आई०/सूचना प्रेषण/2026-27 dated 09/07/2026 transferred this RTI request to BDO Chhanbey / City Mirzapur. Additionally, the applicant filed a Related First Appeal (u/s 19(1)) with registration number COMRD/A/2026/60840 in 2026 before the FAA / Chief Development Officer (CDO), Mirzapur.

In an earlier case about FY 2022–23 works and public information boards, the commission logged an Earlier Second Appeal as Appeal No. S09/A/0494/2025 (Reg. No. A-20250200829) on 16/02/2025. This case started from an RTI dated 11/10/2024 and First Appeal dated 27/11/2024, resulting in a Final Order on 11/05/2026. Furthermore, Hearing Room S-9 of UPSIC Lucknow sent UPSIC Hearing Notices under numbers 2025085098300236 and 202604S09N300614 on 07/08/2025 and 30/04/2026.

Moreover, Secretary Dilip Kumar Yadav’s reply dated 10/05/2026 cited several Earlier Departmental Letters from 2025. These included BDO Letter 707 (13/08/2025), DPRO Letter 4185 (24/01/2025), and DDO Letter 824 (13/08/2025). Additionally, an applicant filed an RTI for Certified Copy of UPSIC Order under registration number UPICM/R/2026/60310 (Reply Letter 305/उ०प्र०सू०आ०/ज०सू०आ०/2025-26) on 22/05/2026. This matched Scrutiny / KOF Diary No. D-220520260032, through which the commission delivered the order dated 11/05/2026. Finally, UPSIC issued the UPSIC Certified Copy Rules Order under reference 248/उ०प्र०सू०आ०/अधिष्ठान/146/2014 on 13/11/2025 as the official guidelines governing document inspection and copies.

2. Concerned Public Authorities & Officials (Emails, Mobiles & Addresses)

District-Level Authorities

The main contact for the Panchayati Raj Department at the district level is SPIO / Respondent No. 1, represented by Shri Ram Uday Yadav (earlier Shri Santosh Kumar), District Panchayat Raj Officer (DPRO), Mirzapur. Citizens can call them at 9506150545 or send an email to dpromi-up@nic.in. Their office is located at the Office of the District Panchayat Raj Officer (DPRO), Mirzapur, U.P. – 231001.

Divisional Appellate Level

Furthermore, the appeals officer at the division level is the First Appellate Authority (FAA) / Respondent No. 2, represented by Shri Samarjeet Yadav, Deputy Director (Panchayat), Vindhyachal Division, Mirzapur. Their telephone number is 8546013760 and email is ddprmi-up@nic.in. Their office address is Office of the Deputy Director (Panchayat), Vindhyachal Division, Mirzapur, U.P. – 231001.

State-Level Oversight

At the state level in the Panchayati Raj Directorate, U.P., the Nodal Officer (State Level), specifically Nodal Officer (RTI), handles general oversight. You can contact them at 9795140577 or up.panchayatiraj@gmail.com at Directorate of Panchayati Raj, Lohia Bhawan, Sector-E, Aliganj, Lucknow, U.P. In addition, Shri Dhirendra Singh Sachan (IAS), Director, Panchayati Raj, Uttar Pradesh, acts as the Head of Department. Citizens can reach him at 0522-2322924 or panchraj@nic.in. His office is at Directorate of Panchayati Raj, Plot No. 6, Lohia Bhawan, Sector-E, Aliganj, Lucknow, U.P.

Local Field Level & Block Supervision

At local levels, duties are split between village staff and block supervisors. Specifically, the Deemed PIO / Respondent No. 3 at the Gram Panchayat level is Shri Dilip Kumar Yadav, Gram Panchayat Adhikari (Secretary), Gram Panchayat Bihasada Khurd. You can reach him by email at dileepline4@gmail.com at Gram Panchayat Bihasada Khurd, Block Chhanbey, District Mirzapur, U.P. – 231303. Meanwhile, the Block Supervisory Authority includes the Block Development Officer (BDO) & ADO (Panchayat), Block Chhanbey. You can email them at bdo.chhanbey96@rediffmail.com at Office of the Block Development Officer, Block Chhanbey (Vijaypur), Mirzapur, U.P.

Commission-Level Proceedings

Finally, state information officers oversee commission-level cases. Specifically, Smt. Shakuntala Gautam, Hon’ble State Information Commissioner (Room S-9), leads the Second Appellate Authority at UPSIC Hearing Room S-9. You can email her at hearingcourts9.upic@up.gov.in at Hearing Room S-9, Uttar Pradesh State Information Commission, RTI Bhawan, Vibhuti Khand, Gomti Nagar, Lucknow – 226010. Additionally, Shri Mumtaz Ahmad (PIO / Admin Officer, Room 404/412) and Shri Tejaskar Pandey (FAA / Deputy Secretary, Room 410/421) manage the UPSIC Registry / PIO & FAA in Lucknow. Citizens can call them at 0522-2724945 (PIO), 0522-2724941 (FAA), or 0522-2724930 (Office). Furthermore, you can reach them by email at jansu-section.upic@up.gov.in or webmaster-upic@up.gov.in at Uttar Pradesh State Information Commission, 7/7A, RTI Bhawan, Vibhuti Khand, Gomti Nagar, Lucknow, U.P. – 226010.

To file and track online RTI applications (DIRPR/R/2026/63290) and First Appeals (DIRPR/A/2026/63586), citizens can access the Uttar Pradesh RTI Online Portal (Govt. of Uttar Pradesh) directly at UP RTI Online Portal.

In addition, official websites of the Uttar Pradesh State Information Commission (UPSIC) handle second appeals and commission steps. First, citizens file and manage online Second Appeals (A-20261103225), upload responses, and join online hearings through the UPSIC Official Website & CATS Portal. Second, tracking application status, diary numbers, and room assignments by Registration No. (A-20261103225) works via the UPSIC Case Status Tracker at UPSIC Application & Appeal Status. Third, reviewing weekly schedules and downloading signed orders for Rooms S-1 to S-11 happens through the UPSIC Weekly Cause List & Orders at UPSIC Weekly Cause List.

Furthermore, two main web resources support rural data and oversight. Citizens can view Gram Panchayat budgets, plan spending, cash books, payment receipts, and Public Information Boards on the eGramSwaraj Portal (Ministry of Panchayati Raj, Govt. of India) at eGramSwaraj Official Portal. Lastly, the Panchayati Raj Department, Uttar Pradesh provides state orders, contact directories, and Panchayat Bhawan updates at UP Panchayati Raj Directorate.

Home » Paper Roads & Phantom Projects: A Case Study

Facing a similar challenge? Share the details in the box below, and our team of experts will do their best to help.

This site uses Akismet to reduce spam. Learn how your comment data is processed.

November 2026
M T W T F S S
 1
2345678
9101112131415
16171819202122
23242526272829
30